5/5 - (3 votes)

Pass Your Exam Easily! SMC Real Question Answers Updated on May 04, 2023

Actual Questions Answers Pass With Real SMC Exam Dumps

How to book the Scrum Master Certified (SMC) Exam

Follow the steps listed below to apply for the Scrum Master Certified (SMC) Exam:

  • Step 1: Visit the Scrum Master Certified (SMC) section under the “Certifications” tab on the SCRUMstudy website.
  • Step 2: Register your account and click Apply for the exam.
  • Step 3: Pay $450 or use a voucher.
  • Step 4: Submit required documents online.
  • Step 5: Access Scrum Master Certified course (Online or Instructor-led) and get a copy of guide books.
  • Step 6: Schedule the two-hour exam online.

 

QUESTION 48
Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during
_________________________.
A) Daily Standup Meetings.
B) Sprint Review Meetings.
C) Release Planning Meetings.
D) Sprint Planning Meetings.

 
 
 
 

QUESTION 49
You are the Scrum Master ofthe JKM Project and your Development Team has asked to change some rules about the duration of the Sprints. Which one of the following statements is a rule of Scrum that the team should follow when it comes to Sprint duration?

 
 
 
 

QUESTION 50
The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the lessons learned during the process. What is an output of this process?

 
 
 
 

QUESTION 51
Is Scrum immutable

 
 

QUESTION 52
Which of the following statements is NOT true of an Impediment Log?

 
 
 
 

QUESTION 53
The Scrum Master coordinates with the Product Owner and other stakeholders to ensure benefits from the project are realized. Which of the following is true about Benefits Realization?

 
 
 
 

QUESTION 54
Which of the following about User Story Acceptance Criteria is true?

 
 
 
 

QUESTION 55
A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This isbecause a large number of customer requirements which changed during the project were not incorporated into the deliverables. The company could have avoided this situation if it had applied the Scrum Methodology, as it would have ensured that any change requested by the customer was included as part of the project, and that the team produced deliverables that were better suited to the final business environment. Which Scrum aspect is being emphasized here?

 
 
 
 

QUESTION 56
Which one of the following is NOT a type of identified dependencies in a Scrum project?

 
 
 
 

QUESTION 57
While performing a cost-benefit analysis, the Product Owner of a project determined that the project has 45% probability of incurring a loss of $800,000 due to the latest Land Reform Bill. Which of thefollowing techniques is being used by the Product Owner to perform cost-benefit analysis?

 
 
 
 

QUESTION 58
As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this regard?

 
 
 
 

QUESTION 59
Which of the following best defines the team velocity metric used to measure team performance?

 
 
 
 

QUESTION 60
Who among the following can directly approve changes recommended in the project?

 
 
 
 

QUESTION 61
Listed below are some responsibilities of a Scrum Master. Identify the one that is NOT correct.

 
 
 
 

QUESTION 62
The senior management of a multi-national company undertakes turnkey projects. To provide better value to customers, the senior management wants to implement Scrum in the organization. Which of the following is NOT a Scrum principle that can be used as a selling point to illustrate the benefits of Scrum to customers?

 
 
 
 

QUESTION 63
The table given below presents some Scrum roles that play an important part in business justification and their responsibilities. Choose the option that correctly matches each role in the left hand column to its action in the right hand column.

 
 
 
 

QUESTION 64
How long is a Sprint Retrospective in a one month Sprint?

 
 
 
 
 

QUESTION 65
Which of the following methods helps estimate the value provided by projects?

 
 
 
 

QUESTION 66
Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to for the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?

 
 
 
 